Construction Update: January 29, 2016

The Pulse ER Construction Project is now 35% complete with 7,300 hours worked. This past week they poured more cement on the 2nd floor of the new addition.

2nd floor slab looking east

The scaffolding system for the west elevation was started and prep work for the ambulance canopy footings. Exterior framing has been as well. 

First floor west exterior framing




Monday, January 25, 2016

Construction Update, January 25, 2016

The Pulse ER Construction Project is now 30% complete with 7,000 hours worked. This past week cement was poured on the 2nd floor of the new addition. We've begun to install hangers and supports for overhead piping and ductwork.

Concrete being poured in the 2nd floor of the new addition. 

The 1st floor of the new addition received lights in the ceilings and is getting ready to be painted next week. 

1st floor of new addition looking east. 

The last of the steel is being installed that ties the new addition into the existing building. 

East side steel erection.



Friday, January 22, 2016

Betty Bierman on Giving to the Pulse ER Campaign

We have been a part of this community for nearly 100 years. Excellent local health care contributes to our sustainability as a community and the Emergency Room is an essential resources for our citizens. Please join us in helping the community live well by supporting the Pulse Emergency Room Campaign at NOCHS!


Featuring Betty Bierman, President of the North Ottawa Hospital Auxiliary