Friday, January 29, 2016

Construction Update: January 29, 2016

The Pulse ER Construction Project is now 35% complete with 7,300 hours worked. This past week they poured more cement on the 2nd floor of the new addition.

2nd floor slab looking east

The scaffolding system for the west elevation was started and prep work for the ambulance canopy footings. Exterior framing has been as well. 

First floor west exterior framing