Construction Update: February 12, 2016

This past week T.L. Masonry finished erecting scaffolding on the west side of the new addition to complete west elevation exterior framing and to prepare for masonry. We began installing roof drainage lines and drains, as well as the metal stairs in the northwest stairwell of the new addition

Canopy steel on the north side. 

First floor interior framing. 

Scaffolding at the north elevation of the addition.